Unity Church of the Hills Expansion Update

Week of March 11, 2011

This slideshow requires JavaScript.

Final prep for the foundation was done and the foundation was poured! There was also trenching and backfilling while protecting tree roots. The window in 139 was also fixed.

Week of March 6

  • Trenching with the rock saw was done this week. The deep trench from the building pad to and through the driveway will be for the fire sprinkler and the domestic water lines. The domestic water line continues on the north side of the parking lot.
  • The trench beside the existing building will be for the sewer lines.
  • After cutting both sides of the trench with the rock saw, the dirt is pushed back into the trench. Afterwards, the workers will excavate the entire trench with a backhoe. The rock saw is used to avoid extensive damage to the tree root system.
  • The plumber has dug the trench for the LP gas line and placed the pipe.
  • The concrete contractor has completed excavation of all the grade beams and is in the process of tying steel, setting forms, and placing the poly moisture barrier. They also poured concrete in the pavilion grade beams.

We hope that this weekly report is helpful and informative. Thank you for your continued financial support of this project and for your ongoing prayers!

This slideshow requires JavaScript.

Each week during the construction of our new Multi-Purpose Building, we will be providing an update on the progress of the work.

  • The drilling and pouring concrete of all the foundation piers is complete.
  • The 6″ fire sprinkler pipe riser was installed and passed CoA inspection.
  • Trenching for all under-slab plumbing was done and installed. It will be inspected by the end of the week.
  • Trenching for grade beams in the pavilion area was done.
  • The grade beam steel was received and the crew is in the process of tying it up. They are tentatively scheduled to pour the concrete in the pavilion grade beams at the first of next week.
  • The utility contractor is in the process of locating existing pipes, laying out new sewer pipe, and continuing the fire sprinkler line out of the building pad.

We hope that this weekly report will be helpful and informative. Thank you for your continued financial support of this project and for your ongoing prayers!

This slideshow requires JavaScript.


Week of Feb. 21, 2001 Update

Each week during the construction of our new Multi-Purpose
Building, we will be providing an update on the progress of the work.
* The drilling and pouring concrete of all the foundation piers is complete.
*The 6″ fire sprinkler pipe riser was installed and passed CoA inspection.
* Trenching for all under-slab plumbing was done and installed. It will be inspected by the end of the week.
* Trenching for grade beams in the pavilion area was done.
* The grade beam steel was received and the crew is in the process of tying it up.
They are tentatively scheduled to pour the concrete in the pavilion grade beams at the first of next week.
* The utility contractor is in the process of locating existing pipes, laying out new sewer pipe, and continuing the fire sprinkler line out of the building pad.
We hope that this weekly report will be helpful and informative. Thank you for your continued financial support of this project and for your ongoing prayers!

Ground Breaking

Ground breaking took place on Sunday