This slideshow requires JavaScript.
Final prep for the foundation was done and the foundation was poured! There was also trenching and backfilling while protecting tree roots. The window in 139 was also fixed.
This slideshow requires JavaScript.
Final prep for the foundation was done and the foundation was poured! There was also trenching and backfilling while protecting tree roots. The window in 139 was also fixed.
We hope that this weekly report is helpful and informative. Thank you for your continued financial support of this project and for your ongoing prayers!
This slideshow requires JavaScript.
Each week during the construction of our new Multi-Purpose Building, we will be providing an update on the progress of the work.
We hope that this weekly report will be helpful and informative. Thank you for your continued financial support of this project and for your ongoing prayers!
Each week during the construction of our new Multi-Purpose
Building, we will be providing an update on the progress of the work.
* The drilling and pouring concrete of all the foundation piers is complete.
*The 6″ fire sprinkler pipe riser was installed and passed CoA inspection.
* Trenching for all under-slab plumbing was done and installed. It will be inspected by the end of the week.
* Trenching for grade beams in the pavilion area was done.
* The grade beam steel was received and the crew is in the process of tying it up.
They are tentatively scheduled to pour the concrete in the pavilion grade beams at the first of next week.
* The utility contractor is in the process of locating existing pipes, laying out new sewer pipe, and continuing the fire sprinkler line out of the building pad.
We hope that this weekly report will be helpful and informative. Thank you for your continued financial support of this project and for your ongoing prayers!
Ground breaking took place on Sunday
This slideshow requires JavaScript.
Go to Love Is Building to find the many ways you can contribute to our building fund.